Fieldbus & Industrial Networking


Case History 198: Cascade control overcomes valve problems

June 2025 Fieldbus & Industrial Networking

A petrochemical refinery requested an audit of several critical base layer control loops. This article discusses a problem found with a valve that controls the flow of fuel to a heat exchanger. The actual temperature control of the exchanger was managed by a cascade master temperature controller, which adjusted the set point of the secondary steam flow controller. This control was crucial, as a significant portion of the plant downstream from the exchanger relied heavily on maintaining the correct temperature at all times. Even small deviations from the desired temperature set point could lead to issues. While the operators reported that the temperature control system was functioning well, the engineering supervisor included it in the audit due to its critical importance.

Why does one use a cascade control system?

Figure 1 illustrates the schematic of a cascade control system that can be used in a heat exchanger, where the process fluid is heated by steam to reach a desired temperature set point. It may seem unusual to some that the output of the temperature controller (the primary or master controller) does not connect directly to the steam valve. Instead, it is directed to the set point of a flow controller (the secondary or slave controller). This flow controller is the actual device responsible for regulating the flow of steam into the heat exchanger.

There are some very good reasons why this is great strategy:

• As discussed exhaustively in my articles, valves are largely mechanical devices and are ‘the weakest link’ in a control loop. They can suffer from all sorts of problems. Typically 70 to 75% of all control valves are generally suffering from some sort of problem, such as hysteresis, nonlinear installed characteristics, incorrect sizing and stickiness, to name just a few. These have been discussed in detail in many of my articles.

• In a stand-alone control loop the controller output (PD) sends a signal to the positioned/actuator/valve combination, which is effectively instructing it to pass a certain amount of the product passing though it so as to satisfy the control requirements. In reality the signal merely opens the valve to a certain position that is proportional to the value of the PD, and it is by no means certain that the valve was sized and calibrated correctly so that it actually is passing the desired quantity though it. One of the main reasons that the flow control loop is incorporated is to ensure that the correct amount of product does actually pass through the valve. If the correct amount is not achieved then the feedback controller will carry on moving the valve until the PV process variable (PV) does actually reach set point (SP).

• The next reason as to why this is a good strategy is the fact that cascade control is normally used on processes with relatively slow dynamics. Now again as discussed in previous articles a fact of life in feedback control is that whereas processes with fast dynamics can be controller reasonably quickly, slow processes can only be controlled slowly. Instability will result if you try and speed up the control. This means that if the valve does not pass the correct amount of product though it, then the temperature controller can only correct for that as well in a very slow manner. Flow control on the other hand generally has extremely fast dynamics relative to slow procedures like temperature and pH, and that means that the cascade secondary flow controller can quickly get the valve to the correct position. The primary controller, which is there to handle the control of a generally much slower process, would on its own,take much longer to get an imperfect valve to the correct position. Therefore the cascade secondary flow loop gets the valve to the correct position relatively quickly, so the valve problem does not impact adversely on the slower temperature process.

People often ask me how to go about tuning cascade loops. It is very simple, and the procedure is to start with the secondary control loop. One puts the set point of the controller of this loop into Local, so it is not affected by the master controller, and then one performs the normal open and closed loop tests on this loop.

Once these are complete, and if the controller is now tuned correctly, then the set point of the secondary controller is placed back in Remote, which is the signal coming from the PD (output) of the master controller. Then, normal open and closed loop tests are conducted on the master loop, and the tuning is calculated.

I think that what confuses people is that when looking at tuning the primary loop it appears that one has to look at two controllers, two transmitters and only one valve, but in actuality just think of the secondary loop as a complete final control element on the output of the master controller, so when you do the open loop step tests to determine the transfer function of the process, all the elements are included in the PV response to a PD change, and the Maths takes care of all those different elements.

I love tuning cascade loops because I know that the cascade effectively eliminates all the valve problems, and one can rely on the fact that the reaction from the step change of PD accurately represents the process and that it is generally not affected by problems in the final control element.

For this case, we will examine the tests conducted on the secondary steam flow control loop in the heat exchanger. Figure 2 illustrates the “As Found” closed-loop test with the tuning settings observed in the controller. The controller was set to local set point, and set point (SP) step changes were implemented.

From the figure, it is evident that during the first upward SP step change, the control response was relatively good, with the process variable (PV) reaching the SP in approximately 40 seconds. However, during the subsequent downward SP step, the flow did not change for about 10 seconds, which suggests that the valve may have been sticking or experiencing hysteresis. Although this behaviour was not too severe, the next upward SP step revealed a different issue. In this instance, the valve took around 17 seconds to respond before it moved, and when it did, the PV overshot significantly. During this delay, the proportional-derivative (PD) controller had ramped up by 4% to prompt movement. Following this, the PD quickly reversed, causing the PV to drop below the SP and remain there while the PD slowly increased again to bring the PV back to the SP. When the SP was stepped down by 1,5%, the PV remained unchanged until the test concluded, with the PD gradually ramping down while trying to position the valve correctly.

This test shows that there are relatively bad problems with the final control element, consisting of the positioner/valve combination. There is possibly hysteresis or stickiness and an element of instability, as seen with the big valve overshoot. These facts were confirmed by the Open Loop Test, part of which is displayed in Figure 3. It can be seen from this test that:

• The valve is about 2,5 times oversized (Ratio of PV change to PD change). This is not good, as oversized valves, as oversized valves multiply all faults in the valve by the oversized value.

• There is about 2,5% hysteresis on the valve, which is not too good.

• The valve is sticky, as it takes quite some time for the positioner to get it to the correct place after a step.

• There is a massive overshoot on the steps when opening the valve. This is bad.

• When checking the tuning from the steps in the test, it was seen that the original tuning, as found in the controller, was quite satisfactory.

• Figure 4 shows a final Closed Loop test with a slightly faster tune. Here, it can be seen that the control performance was very similar to that seen in the first as-found Closed Loop Test. Noticeable delays occurred when setpoint (SP) adjustments were made, while the proportional-derivative (PD) control action increased to move the valve through its hysteresis and stickiness. This also highlights the challenges faced by the controller in achieving the process variable (PV) to match the setpoint precisely.

However, as mentioned earlier, the temperature control surprisingly performed well despite the valve issues, demonstrating the effectiveness of the cascade strategy. If the temperature controller’s PD had been directly connected to the final control element, it is very unlikely that the temperature would have reached the setpoint.



About Michael Brown

Michael Brown is a retired specialist in control loop optimisation, with over 50 years of experience in process control instrumentation. His main activities were consulting and teaching practical control loop analysis and optimisation. He presented courses and optimised controls in numerous plants in many countries around the world. Michael is continuing to write articles based on the work he has done, and his courses are still available for purchase in .PDF format. He is still handling the sales of the Protuner Loop Optimisation software. He is happy to answer questions people may have on loop problems.


Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

A one-stop-shop for industrial
Fieldbus & Industrial Networking
HMS Networks has announced that Red Lion and N-Tron are officially product brands. For thousands of automation engineers and system integrators worldwide, this means that scalable industrial solutions for cloud connectivity, edge intelligence, asset management, industrial Ethernet switches, panel meters and operator panels are now available from one trusted source.

Read more...
Power over Ethernet (PoE) injector for seamless deployment
Vepac Electronics Fieldbus & Industrial Networking
The Edimax GP-203IT from Vepac Electronics is a Power over Ethernet injector that not only delivers a cost-effective solution for power distribution, but also enables seamless deployment on the existing LAN infrastructure.

Read more...
A one-stop-shop for industrial communication
Fieldbus & Industrial Networking
HMS Networks has announced that Red Lion and N-Tron are officially product brands. For thousands of automation engineers and system integrators worldwide, this means that scalable industrial solutions for cloud connectivity, edge intelligence, asset management, industrial Ethernet switches, panel meters and operator panels are now available from one trusted source.

Read more...
Cost-effective industrial PoE injector
Vepac Electronics Fieldbus & Industrial Networking
The Edimax IGP-203IT from Vepac Electronics is an industrial PoE injector that not only delivers a cost-effective solution for power distribution, but also allows seamless deployment on an existing LAN infrastructure.

Read more...
Harnessing the power of OT networking
RJ Connect Fieldbus & Industrial Networking
Businesses are increasingly embracing IT/OT convergence to stay ahead and capitalise on advantages such as smarter factories and higher efficiency. This article provides practical insights and guidance to help you navigate these challenges effectively.

Read more...
PC-based control for advanced hydrogen storage technology
Beckhoff Automation Fieldbus & Industrial Networking
Sufficient storage options for renewable energies are essential to use them as efficiently as possible. GKN Hydrogen offers a particularly compact and safe option, low-pressure metal hydride hydrogen storage systems with PC-based control from Beckhoff.

Read more...
Power over Ethernet splitter without electric cabling
Vepac Electronics Fieldbus & Industrial Networking
The GP-101ST Gigabit PoE (Power over Ethernet) Splitter from Vepac Electronics delivers both data and electrical power to non-PoE Fast Ethernet or Gigabit Ethernet-enabled products such as network cameras and wireless access points, using an Ethernet cable, without the need for power outlets and electrical cabling.

Read more...
Beckhoff’s XPlanar boosts productivity in medical device assembly
Beckhoff Automation Fieldbus & Industrial Networking
The intelligent transport system, XPlanar from Beckhoff provided the basis for an innovative system concept allowing the specialists at Automation NTH to reduce the space requirement of an assembly machine for medical diagnostic devices by a factor of 10.

Read more...
Comprehensive solutions for the food and beverage sector
RS South Africa Fieldbus & Industrial Networking
RS South Africa is reinforcing its commitment to the country’s dynamic food and beverage sector, backed by a comprehensive portfolio of over 800 000 products, extensive technical expertise and end-to-end service capabilities.

Read more...
Improved networking technology for fire and gas detection
Omniflex Remote Monitoring Specialists Fieldbus & Industrial Networking
Critical alarm and event management technology supplier, Omniflex has worked with the South African Nuclear Energy Corporation to upgrade equipment providing digital and analogue signals for its safety critical fire and gas alarm systems.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved