IT in Manufacturing


Digital revolution in transformer substations

February 2025 IT in Manufacturing

The energy sector is under a lot of pressure. Distribution grid operators need to get their infrastructure ready for the energy transition and fast. By 2030, some 80 percent of electricity is to be generated from renewable sources. A pilot project at naturenergie netze in Germany is demonstrating how transformer substations can be modernised more quickly. In collaboration with software suppliers Eplan and entegra, this southern German distribution grid operator is now working for the first time on a digital twin that will greatly speed up the planning and further development of transformer substations.

In the past, there was distribution. For decades, energy was simply distributed in one direction, from continuously operating coal and nuclear power stations to transformer substations, and from there to end consumers once the voltage had been stepped down several times. To use a road traffic analogy, this quiet one-way street has now become a busy city centre road network. Nowadays, the energy mix changes hourly with the wind and weather, so essentially there isn´t a reliable base load any more. Wind farm and solar system operators feed in energy decentrally at medium- and low-voltage levels, so power grids now work in two directions. Heat pumps and electric vehicle charging stations mean higher consumption, while familiar load profiles that peak in the early evening are now a thing of the past. However, both the quality of the supply and the 50 Hz frequency must be guaranteed at all times.

Grid operators are facing a mammoth task. They need to make their grids fit for these complex requirements. For naturenergie netze, this involves new construction work, as well as modernising a number of existing transformer substations. The plants need to be adapted to suit the increasing demand for electricity, but that isn´t the only challenge. A bigger challenge is that they need to be adapted to cope with a much higher level of flexibility in terms of energy sources and flows and the precise control of electricity.

A digital twin

naturenergie netze was quick to address these challenges and is currently working on a pilot project as it modernises one of its systems. The grid operator is using a digital concept to plan and configure its conversion of the Rheinfelden transformer substation. The new approach applies even to the preliminary work. Rainer Beck, a grid development coordinator, explains: “Before we start planning, we create a digital twin of the transformer substation. This is a virtual representation with all the data for both the live components (the primary technology) and the control level (the secondary technology) and, of course, for the buildings and all the peripherals. We then plan the conversion on the basis of this digital twin.”

Another reason why this is a challenging task is that the primary and secondary technologies are planned using different CAD software tools. In this pilot project, this issue was resolved by a very special collaboration. Among members of the VDE ETG ‘digital twins for electrical energy systems’ task force there were two leading suppliers, entegra with its primtech software solution for the primary technology and Eplan for the secondary technology. Both had prepared for precisely what naturenergie netze needed for the first planning stage, namely combining primary and secondary technology in a single model.

Major efficiency gains

For this unique project, entegra and Eplan were looking for an innovative distribution grid operator with a suitable pilot project to get involved as the third party in this collaboration. Contact with naturenergie netze came at exactly the right time, especially since the project in question was a complex one. As Beck explains: “The aim of the project is to renew all the secondary technology in an existing, highly complex transformer substation during ongoing operations. It´s easy to understand why involvement in this project was appealing. It would normally take two to three years to plan and implement the modernisation, but the new planning methodology will really speed things up. Everybody involved in the project agrees.”

Matthias Schuy, business development manager at entegra, explains: “What we´re doing here is integrating a transformer substation´s primary and secondary technology into one digital twin. This has never been done before, but promises major benefits.” Beck adds: “Ultimately, we need to prove that the one-off investment will pay off quickly. After the first project phase, the preliminary planning, we see considerable time savings during the actual conversion of the transformer substations. What´s more, this applies to every project.”

One model for all users

During the first stage of the project, the transformer substation was scanned, photos were taken of the rating plates, and the primary technology data generated was compared with the data from the asset management system. The result was a valid, functional primtech 3D model of the transformer substation. During a fully automated process, the datasets created in primtech were then exported to Eplan via an interface and used as the basis for planning the secondary technology in Eplan. Finally, the data from the secondary technology was integrated into the digital twin. By documenting the scenario as it currently stands, the basis has been provided for replacing the transformer substation´s secondary technology efficiently. “This is a really important step. All the data is verified. We basically follow the ´single source of truth´ principle. The data in the original systems is left untouched and linked to the digital twin. This prevents redundancies that could prove problematic in the future,” explains Jan Oliver Kammesheidt, global vertical market manager for Energy at Eplan.

In terms of the architecture of the combined data model, the parties involved have created a special infrastructure. “There´s no leading system. Instead, there are merely different perspectives of one and the same model. The digital twin opens a window to the systems, for example, from primtech to Eplan or SAP. The digital twin therefore fulfils one of its main functions, namely offering centralised access to all relevant information for the transformer substation,” Schuy explains.

Standardising secondary technology

This collaboration by the three parties − entegra, Eplan and the distribution grid operator − was made possible, or at least made easier, by a decision taken two years ago. That was when naturenergie netze started using the Eplan Electric P8 and Eplan Pro Panel software solutions to plan its secondary technology − its control technology. Simon Rümmele, the grid development project leader, was responsible for this. “With Eplan, we can drive forward the standardisation and more efficient engineering of the secondary technology, and also use end-to-end planning during the operation phase for preventive maintenance and overhauls,” he says.

Lessons from mechanical engineering

The project is demonstrating that users in the electricity industry are benefiting from experience and solutions from mechanical engineering. In that sector, one in which Eplan has been active for decades, standardisation and industrialisation of panel building and switchgear manufacturing equipment is firmly established. As regards this step for transformer substations, there is still a lot of catching up to do, but it has to happen. “Up until now, transformer substations have been planned on a case-by-case basis and built as one-offs. However, this makes it very difficult to judge the need for modernisation and new-builds that are arising as a result of the energy transition. The sector needs to standardise much more than it has in the past. We are providing support and are delighted to have found an innovative partner in naturenergie netze. With the joint digital twin for primary and secondary technology, we are speeding up the process considerably and making it more reliable, too,” Kammesheidt explains.

Strong partners for the conversion

Rümmele says this is precisely what naturenergie netze is setting out to achieve. “We want and need to digitalise more, because we believe this will open up opportunities and make things easier in the future. That´s why we´re trying out the latest technologies and planning further pilot projects at our transformer substation in Rheinfelden. What´s more, with Rittal, the sister company of Eplan, we also have a strong partner on board for converting the hardware, in other words all the enclosure technology,” he explains.

naturenergie netze has also been planning standardisation for some time now, and the joint digital twin created by entegra and Eplan will provide the basis for this, too. Rainer Beck says: “We can envisage using two standard concepts and buildings in the 110 kV range and creating variants on the basis of these. We´re also working on this with the main primary suppliers. This will cut down the amount of time and planning required. This is vital, because we´re going to be forced to adapt the majority of our transformer substations to comply with the new requirements. The digital twin and the preliminary work being carried out by entegra and Eplan will help us with this. Through partnership and collaboration, we are coming up with a genuine innovation that will help us develop our grids and make them fit for the future efficiently.”

However, it is not only naturenergie netze who will benefit from the project. Kammesheidt concludes: “In contrast to the mechanical engineering sector, grid operators openly share information, because they´re not competing with each other. There´s already a lot of interest. I´m convinced that many grid operators can take what we´re doing here and in the VDE task force to plan and implement their conversion and new-build projects faster.”


Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Unlocking mining efficiency with advanced processing control
IT in Manufacturing
ABB’s Advanced Process Control system, powered by its Expert Optimizer platform, is emerging as a key enabler of smarter, more efficient mining operations.

Read more...
PC-based control regulates innovative dehumidifiers
Beckhoff Automation IT in Manufacturing
The Swedish company Airwatergreen AB is breaking new ground in the dehumidification of air in industrial buildings and warehouses. PC-based control from Beckhoff regulates the innovative process.

Read more...
Harnessing AI and satellite imagery to estimate water levels in dams
IT in Manufacturing
Farmers and water managers often struggle to accurately estimate and monitor the available water in dams. To address the challenge, International Water Management Institute researchers have worked with Digital Earth Africa to create an innovation that uses satellite images and AI to get timely and accurate dam volume measurements.

Read more...
Why industry should enter the world of operator training simulators
Schneider Electric South Africa IT in Manufacturing
System-agnostic operator training simulator (OTS) software is a somewhat unsung hero of industry that trains plant operators in a virtual world that mirrors real-world operations. The benefits are multiple.

Read more...
Track busway for scalable data centre power delivery
IT in Manufacturing
The latest generation Legrand Data Centre Track Busway technology addresses the operational pressures facing today’s high-density, AI-intensive computing environments and is being well received by data centre facilities around the world.

Read more...
Poor heat management in data centre design
IT in Manufacturing
Designing a world-class data centre goes beyond simply keeping servers on during load shedding; it is about ensuring they run efficiently, reliably, and within the precise environmental conditions they were built and designed for.

Read more...
It’s time to fight AI with AI in the battle for cyber resilience
IT in Manufacturing
Cybercrime is evolving rapidly, and the nature of cyber threats has shifted dramatically. Attacks are now increasingly powered by AI, accelerating their speed, scale and sophistication. Cybersecurity needs to become part of business-critical strategy, powered by AI to match attackers’ speed with smarter, faster and more adaptive defences.

Read more...
Why AI sustainability must be a boardroom priority
IT in Manufacturing
As South African companies race to harness artificial intelligence for innovation and growth, few are asking the most critical question - the environmental cost.

Read more...
RS South Africa shines spotlight on MRO procurement
RS South Africa IT in Manufacturing
RS South Africa has highlighted the growing pressures faced by procurement professionals responsible for maintenance, repair and operations supplies across the country’s vital economic sectors.

Read more...
Sustainable energy management
Siemens South Africa IT in Manufacturing
Utilising its innovative ONE approach technology, Siemens provides complete transparency on resource consumption and offers data-driven optimisation recommendations for sustainable energy management.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved