Maintenance, Test & Measurement, Calibration


Taking projects to completion: site acceptance testing, commissioning and handover

January 2008 Maintenance, Test & Measurement, Calibration

It is a sad fact of life that one regularly hears about contractors having left a site before a project has been completed. This is often the result of either not having a proper specification or not working to the specification.

With more than 100 years of combined engineering experience in the fields of plant automation, simulation, optimisation and information systems in mineral processing and related industries, systems engineering and integration company Iritron has achieved a sound track record of project successes.

The company attributes these successes to its disciplined approach to project management. This procedure describes how it has formalised the steps of project acceptance testing, commissioning and handover.

Objectives

The goals of a formal project acceptance testing, commissioning and handover procedure are:

* To define areas of responsibility and acceptance.

* To clarify and define different phases of acceptance and handover.

* To record items outstanding for phase or project completion on a punch list.

* To minimise outstanding work at the various phases or project start up.

* To optimise plant start up.

* To determine whether design characteristics and parameters are met.

* To ensure technical acceptability of plant and equipment.

Procedural overview

During testing and commissioning the project manager, with the assistance of the commissioning team, monitors the equipment and plant installation, operation and performance, along with safety and project schedule. Monitoring takes place on both informal and formal bases, with the latter consisting of official check lists and punch lists.

There are two distinct phases of the punch listing procedure viz. acceptance testing (first punch) and process commissioning (second punch). The first punch list is compiled by the acceptance testing manager and the second punch list by the commissioning manager with critical items clearly indicated. The completion of both punch lists is the responsibility of the project manager. However, the acceptance of the completion of the second punch list is the direct responsibility of the commissioning manager following the criteria set in the relevant contract documents and procedures.

Acceptance testing check lists

Check lists are used by the acceptance testing team and the commissioning team to assist in the monitoring of the equipment installation. The checklists are issued to both the contractor and the commissioning team. The project manager's acceptance testing team ensures that all equipment is installed correctly and ready for acceptance testing. On completion of the installation, both the contractor and the project manager sign off the checklists. The signing of the checklists does not constitute acceptance by the owner or the project manager of any portion of the works.

The works and the equipment remain the responsibility of the contractor until the Acceptance of Works Certificate is issued. It is the contractor's duty to ensure that all precautions are taken to protect the equipment and plant against loss or accidental damages until this certificate is issued.

First test: installation

The mechanical, electrical and instrumentation (MEI) acceptance testing teams check for the correct installation of equipment by the contractor during construction.

The teams check that all equipment is installed as designed. If any modifications are required, these must be noted and channelled through the acceptance testing manager to the construction manager. All installation errors or potential errors should be identified as early as possible to prevent rework by the contractor. Checklists are used to control the monitoring and acceptance of the correct installation of the equipment prior to power being switched on.

This project phase is complete once the installation checklist has been completed and signed off by the contractor and commissioning manager's representative for all items of equipment.

Second test: functional

The acceptance testing teams test each individual device or piece of equipment to ensure that all components of the plant function correctly from the scada to PLC to I/O racks, to all field equipment for outputs or the reverse for inputs.

During this testing phase fine adjustments are made to field equipment to ensure correct operation.

The contractor's technicians check the operation of all equipment to ensure correct operation of the drives and motors.

The MEI and operations acceptance testing teams check for correct operation of the equipment once the contractor has completed the installation and the first test checklist has been signed off. Power is connected to the equipment, direction testing is checked and equipment is run as individual units.

All critical items that will prevent a system from running are noted on a list forming part of the first punch list for rectification by the contractor.

This testing phase is completed for an item of equipment once all critical items on the first punch list have been corrected and the checklist has been signed off by the contractor and the commissioning manager's representative. At this point the unit is ready to be run as part of a system.

Third test: system

On completion of the second test, the MEI and operations acceptance testing team run each system to check interlocking and ensure that the plant is ready to accept feed.

Wet and dry calibrations are carried out as part of this testing phase where this is practical.

The commissioning teams punch list the systems with items listed as critical and non-critical.

This test phase is considered complete for a system when the critical items on the punch list have been rectified and the contractor and the commissioning manager's representative have signed off the checklist.

The plant is now handed over to operations personnel for process commissioning.

Fourth test: process commissioning

From this point, routine maintenance is the responsibility of the owner. Abnormal maintenance and properly authorised scope changes are attended to by the contractor and supervised by the project manager's construction teams.

In this test phase, feed is introduced into the plant for the first time and the systems are brought up to nominal operating throughput.

The second punch list is produced by the process commissioning team and all critical items are rectified prior to the commencement of the performance test.

The performance test is carried out to ensure that the entire plant is capable of operating continuously at nominal throughput for a period of not less than 24 hours.

The Final Acceptance Certificate is issued to the contractor on completion of all the items on the second punch list.

Project close-out

Project close-out is considered complete with the notification to the owner's management and project department of the completion of the project with respect to:

* As-built drawings.

* Operation manuals.

* Maintenance manuals.

* Spares requirements.

* Cost reconciliation

* Contractual documentation.

* Contract special conditions.

* Performance data.

* Standard operating procedures.

* Design calculations.

* Warranties.

* Project assessment and justification with respect to original justification.

For more information contact Alwyn Rautenbach, Iritron, +27 (0)12 349 2919, [email protected], www.iritron.co.za



Credit(s)



Share this article:
Share via emailShare via LinkedInPrint this page

Further reading:

Oils don’t die, they degrade
Wearcheck Maintenance, Test & Measurement, Calibration
WearCheck explores the main ways lubricants degrade in service and how these degradation modes affect oil performance and machine reliability.

Read more...
Real-time spectrum analyser
Vepac Electronics Maintenance, Test & Measurement, Calibration
The PXE series real-time spectrum analyser covers frequencies up to 20 GHz with a 100 MHz analytical bandwidth and ultra-fast sweep speed, supporting spectrum monitoring, interference finding and RF test and measurement functions.

Read more...
Preserving a French heritage landmark
Omniflex Remote Monitoring Specialists Maintenance, Test & Measurement, Calibration
Omniflex supplied a remotely monitored impressed current cathodic protection system for the Perret Tower in Grenoble, a protected French heritage site, combining 24/7 corrosion protection with integrated surge protection against lightning strikes.

Read more...
Operational efficiencies and safety compliance with preventive maintenance programmes
Maintenance, Test & Measurement, Calibration
Konecranes explains how its Lifecycle Care Preventive Maintenance programme reduces unexpected downtime, improves safety compliance and delivers measurable financial benefits for operators of cranes and lifting equipment across any make or sector.

Read more...
Portable appliance tester
Vepac Electronics Maintenance, Test & Measurement, Calibration
Vepac Electronics’ new portable appliance tester enables precise safety testing of electrical appliances in accordance with DGUV regulation 3 and BetrSichV, with simple three-button operation and battery-powered mobility.

Read more...
Why lubrication fails in mining and what to do about it
Maintenance, Test & Measurement, Calibration
Lubrication Engineers explains the recurring failure points behind mining lubrication problems and how the right product, storage and application practices can improve equipment reliability.

Read more...
When digital twins move from concept to critical tool
IT in Manufacturing System Integration & Control Systems Design Maintenance, Test & Measurement, Calibration
Digital twins are moving out of the lab and onto the mine, the factory floor and the transport network where they predict failures before they happen. Amritesh Anand looks at where they earn their keep, the data and integration work behind them, and the security questions every organisation should ask before switching one on.

Read more...
Why asset level intelligence is now essential for resilient wastewater plants
Schneider Electric South Africa Maintenance, Test & Measurement, Calibration
Sub-Saharan Africa’s wastewater operators face mounting pressure to keep ageing plants running smoothly and meet tougher environmental standards, all while lacking visibility into the health of their medium-voltage (MV) drives and other critical rotating assets. Adding predictive analytics, digital twins and enterprise dashboards enables optimisation across multiple sites, ensuring every drop moves safely and efficiently through the water cycle.

Read more...
How multiple boilers can minimise costly downtime
Maintenance, Test & Measurement, Calibration
Associated Energy Services explains how multi-boiler systems reduce downtime risk for South African manufacturers, covering redundancy planning, fuel source diversification and the strategic management of backup boiler capacity.

Read more...
Field calibration made easy
Instrotech Maintenance, Test & Measurement, Calibration
Instrotech’s locally designed and manufactured Calog calibrator range feature a rugged IP54-rated housing, backlit display with data logging via SD card, and a lithium-ion battery with approximately eight hours of run time.

Read more...









While every effort has been made to ensure the accuracy of the information contained herein, the publisher and its agents cannot be held responsible for any errors contained, or any loss incurred as a result. Articles published do not necessarily reflect the views of the publishers. The editor reserves the right to alter or cut copy. Articles submitted are deemed to have been cleared for publication. Advertisements and company contact details are published as provided by the advertiser. Technews Publishing (Pty) Ltd cannot be held responsible for the accuracy or veracity of supplied material.




© Technews Publishing (Pty) Ltd | All Rights Reserved